Each process of construction is directly or indirectly related to the other. Having a bit of knowledge about each one of these is imperative even if you specialize in only one, like residential electrical construction.

East-West Electric explains the phases of residential electrical construction so you can better understand your home electrical installation.

Phases of Electrical Construction

From a contractor’s perspective, there are two main stages for the construction of a house: wet and dry. 

The wet stage refers to when the house is unprotected from moisture caused by external forces such as rain. However, the dry stage is when most electrical work is carried out as it is safe from rain and snow.

On the other hand, from an electrician’s perspective, the two main phases of construction include phase one – the rough-in, and phase two – the finish. 

A Step-by-Step Guide Into How the Electrical Work is Carried Out During the Construction of a House

Stage 1 – Temporary Electric and Underground Conduit

Installation of a temporary electric pole takes place here since there is a lot of machinery that operates on electricity. And, there is no electricity connection at the construction site.

A generator may also be used in its place. Before the floor is finalized with concrete, electrical conduits are laid down, mainly if the floor plan includes receptacles.

It is the only step that takes place in the wet phase. It can usually be completed in a few hours.

Stage 2 – The Rough-in

This stage comes once all the floors, windows, doors, etc. have been installed. But, the sheetrock is still left to be installed. It is mainly centered on circuit wiring between the electric box and wall studs by drilling holes where necessary.

Exhaust fans and can lights are also put up and fixed. And, since the installation of roofing is during this stage, if you have lights on the soffit in plans, here is when you put those up.

Then, all wiring related to the entertainment system, security system, etc. are also installed. This can take a few days for small homes up to a few months for larger ones.

Stage 3 – More Temporary Needs

This stage covers a lot of small details. When they lay the sheetrock has and no significant electrical wiring changes can take place now. They temporarily add receptacles in locations like the garage to allow convenient entrance and exit from the house.

Temperature control systems are installed in addition to a few lights and switches. These are expected to be damaged by sheetrock mud and paint, so installation is only temporarily. This stage can usually be completed in one day.

Stage 4 – The Finish

At the final stage,  the installation of all switchboards, fans, lights, receptacles, HVAC systems, and external electrical items takes place.

This process can take a few days for small houses and between a few weeks and a few months for larger homes.

Stage 5 – Modifications and Warrant

This stage is the testing stage. This is where everything is checked to see whether the wiring has been done correctly or not. So, if a fan has been miswired or a light doesn’t work, it can be fixed even after the owner moves in.

Residential Electrical Construction in Clearwater, FL

At the heart of any residential or commercial property is the electrical setup. Choosing the right electrical design team is one of the most important aspects of any construction or renovation project. At East-West Electric, we offer comprehensive electrical construction services for a variety of purposes and industries. From residential construction to larger buildings and complexes, our team is on hand to offer the advice you need.  Contact East-West Electric for a consultation today!